Deferment of possession
Contracts generally grant the contractor exclusive possession of the site until practical completion when a handover meeting takes place and possession reverts to the client (see handover to client). The contract may state the date for possession of the site by the contractor (sometimes called the 'commencement date'), or, if not, then the site must be handed over to the contractor within a reasonable time after signing of the contract.
Some contracts (such as the JCT Standard Form of Building Contract) will entitle the client to defer giving the contractor possession of the site for a period of up to six weeks unless a shorter period was stipulated in the contract particulars (it is probably unwise to reduce the period). This provision enables the client to defer possession without being in breach of contract.
It is considered that deferment of possession is a positive activity which the employer should signal by giving written notice although that is not expressly stated.
Deferment of possession can be considered a relevant matter, giving rise to the possibility of the contractor claiming an extension of time or loss and expense. However, for such a claim to succeed, the deferment must have a material effect on the regular progress of the works. Obviously, deferment will have an immediate effect on progress, however, it does not extend the contract period, it simply moves it in time with dates for possession and completion which continue to have the same relationship to each other.
If the contractor is given early notice of deferment, they are likely to incur far fewer costs than if the deferment is only notified a few days before start on site. Issues that might be considered include:
- Plant hire.
- The possibility of using operatives elsewhere.
- Delivery dates
- Key dates for sub-contractors
- The possibility of increased costs and interest charges.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
The context, schemes, standards, roles and relevance of the Building Safety Act.
Retrofit 25 – What's Stopping Us?
Exhibition Opens at The Building Centre.
Types of work to existing buildings
A simple circular economy wiki breakdown with further links.
A threat to the creativity that makes London special.
How can digital twins boost profitability within construction?
The smart construction dashboard, as-built data and site changes forming an accurate digital twin.
Unlocking surplus public defence land and more to speed up the delivery of housing.
The Planning and Infrastructure Bill
An outline of the bill with a mix of reactions on potential impacts from IHBC, CIEEM, CIC, ACE and EIC.
Farnborough College Unveils its Half-house for Sustainable Construction Training.
Spring Statement 2025 with reactions from industry
Confirming previously announced funding, and welfare changes amid adjusted growth forecast.
Scottish Government responds to Grenfell report
As fund for unsafe cladding assessments is launched.
CLC and BSR process map for HRB approvals
One of the initial outputs of their weekly BSR meetings.
Architects Academy at an insulation manufacturing facility
Programme of technical engagement for aspiring designers.
Building Safety Levy technical consultation response
Details of the planned levy now due in 2026.
Great British Energy install solar on school and NHS sites
200 schools and 200 NHS sites to get solar systems, as first project of the newly formed government initiative.
600 million for 60,000 more skilled construction workers
Announced by Treasury ahead of the Spring Statement.
The restoration of the novelist’s birthplace in Eastwood.
Life Critical Fire Safety External Wall System LCFS EWS
Breaking down what is meant by this now often used term.
PAC report on the Remediation of Dangerous Cladding
Recommendations on workforce, transparency, support, insurance, funding, fraud and mismanagement.
New towns, expanded settlements and housing delivery
Modular inquiry asks if new towns and expanded settlements are an effective means of delivering housing.